ISOPROTECT L.P. has executed the following Projects:

INSULATION WORKS OF DUCTS, FILTERS & HEATER - TERNA MAG Worksite - MANTOUDI EVVOIAS (Completed)

The scope of work includes the whole insulation material supply (main insulation, jacketing, ancillary and consumable materials) and application/installation according to the following classes of work.

1. Hot insulation of piping, including insulation of new furnace in Terna MAG-Worksite
2. Hot insulation of rectangular ducts
3. Hot insulation of equipment (Filters)
4. Insulation of piping& ducts for personnel protection
5. Insulation of equipment for personnel protection


• Assignment Date :
• Project Duration : Completed
• Project Budget :

see photos

INSULATION WORKS OF NATURAL GAS NETWORK: PIPING SYSTEMS & EQUIPMENT, HEL.PE. E.I.C. (On Progress)

The scope of work includes the whole insulation material supply (main insulation, jacketing, ancillary and consumable materials) and application/installation according to the following classes of work.

1. Hot insulation of piping, including insulation of vessel 33-V-008 & Exchanger 33-E-022.
2. Hot insulation of equipment
3. Hot insulation for traced piping
4. Insulation of piping for personnel protection
5. Insulation of equipment for personnel protection

• Assignment Date :
• Project Duration : (On Progress)
• Project Budget :

see photos

INSULATION WORKS OF DUCTS & EQUIPMENT - PROJECT BY-PASS SYSTEM - TITAN S.A. - KAMARI CEMENT FACTORY (On Progress)

A Major EPC Project, in the field of CementIndustry. The Project includes the whole insulation material supply (main insulation, jacketing, ancillary and consumable materials) and application/installation according to the following classes of work.

1. Hot insulation of straight ducts (Diam. 50mm-2000mm)
2. Hot insulation of Special Items (Elbows/transitions/rectangular-Diam. 50mm-2000mm)
3. Hot insulation of equipment (Filters, Hoppers, Fans etc.)
4. Insulation of ducts for personnel protection
5. Insulation of equipment for personnel protection


Assignment Date :
Project Duration : (On Progress)
Project Budget :

see photos

INSULATION WORKS OF PIPING AND EQUIPMENT UNIT 100 - PROJECT RELU-6417-A - MOTOROIL HELLAS REFINERY (Completed)

The scope of work have included the whole insulation material supply (main insulation, jacketing, ancillary and consumable materials) and application/installation according to the following classes of work.

1. Hot insulation of piping, including insulation of new furnace F-151 piping
2. Hot insulation of equipment
3. Hot insulation for traced piping
4. Insulation of piping for personnel protection
5. Insulation of equipment for personnel protection
6. Insulation of instrument and instrument lines


Assignment Date :
Project Duration :(Completed)
Project Budget :

see photos

INSULATION WORKS OF U-5150 - HELPE - ASPROPYRGOS REFINERY (Completed)

The business objective of the Contractorship was the supply, prefabrication and erection of hot insulation of piping and equipment of New Steam Boiler Interconnecting Unit 5150.
As insulation contractor of the project our company has undertaken and finally completed all requirements according to the Project Specifications, Drawing and Documents.

Assignment Date : 31/10/2013
Project Duration : 30 Days
Project Budget : 40.000,00 Euros

see photos

INSULATION WORKS OF EQUIPMENT -TITAN S.A. - KAMARI CEMENT FACTORY (Completed)

The business objective of the Contractorship was the supply, prefabrication and erection of hot insulation of Recirculation Fan of Mill No 1, Part of Cooling Tower and Fume Duct of Rotary Incinerator No 1. As insulation contractor of the project our company has undertaken and finally completed all requirements according to the Project Specifications, Drawing and Documents.

Project Budget : 11.000,00 Euros

see photos

INSULATION WORKS OF PIPING AND EQUIPMENT DURING SHUT DOWN WORKS 2014 - HELPE - ELEFSINA REFINERY (Completed)

Analytically the works executed were:

1. On site measurements for prefabrication.
2. Detail study for the correct type of insulation based to E.R.U.P. standards.
3. Materialsupply.
4. Prefabrication works and installation on product and high steam pipes and equipment (vessels, heat exchangers, valves etc.).
5. Dismantling of existing insulation for inspection purposes on pipe and equipment and reinstallation.


All works were executed in presence of HEL.PE. Technical and inspection department. The execution of the project was utterly satisfying and promptly delivered.

? AssingmentDate: 01/04/2014
Project Duration: One (1) month.
Project Budget: 100.000,00 Euros
FinalCost: 112.931,77 Euros

see photos